PennDOT to Begin Second Section of the Route 309 Connector Project in Montgomery County

(The following information was provided by the Pennsylvania Department of Transportation.)

The Pennsylvania Department of Transportation (PennDOT) announced on Tuesday that construction will begin on Monday, Jan. 3 on an improvement project to construct a new roadway alignment to connect Wambold Road from Allentown Road to the Hatfield/Souderton Pike intersection in Franconia and Hatfield townships, Montgomery County.

This project, Section HT2, covers 2.3 miles and is the second of three contracts to move to construction to build the five-mile-long Route 309 Connector in Montgomery and Bucks counties to enhance mobility and safety for motorists traveling between Route 309 and the Pennsylvania Turnpike Interchange.

The first section, Section HAT, was completed in 2012 and included rebuilding and realigning approximately 1.5 miles of Wambold Road from Route 63 to Allentown Road in Franconia Township.

The final section of the Route 309 Connector project, Section HT3, from Hatfield/Souderton Pike to County Line Road, Route 309 and Fairhill Road in Hatfield and Franconia townships, Montgomery County, and Hilltown Township, Bucks County, is currently in preliminary engineering.

Under Section HT2, PennDOT's contractor will:  

  • Construct a new roadway from Allentown Road to the Hatfield/Souderton Pike intersection
  • Reconstruct Township Line Road from Cowpath Road to Hatfield Souderton Pike
  • Replace two culverts
  • Construct two retaining walls
  • Build six noise walls on both sides of Wambold Road between Elroy Road and Cowpath Road
  • Install four new traffic signals and removing and replacing two others
  • Upgrade the traffic signals along existing Wambold Road to a new adaptive system  
  • Upgrade pedestrian facilities
  • Construct stormwater management facilities throughout the project
  • Perform various drainage, roadway and signing improvements
  • Construct 1.5 miles of multi-use trail between Allentown Road and Cowpath Road
  • Perform improvements to the Route 63 (Old Forty Road) and Pennsylvania Turnpike EZ Pass ramp intersection in Towamencin Township
  • Perform off-site traffic signal improvements in Lower Salford and Towamencin townships  

Beginning Monday, Jan. 3, several construction activities will get underway through the winter into early spring 2022, including clearing, erosion and sedimentary control and construction of a temporary access road. Traffic will not be impacted by any of these operations.

During construction on Section HT2, several closures and detours will be implemented as needed by the contractor. Most construction activities will take place during off-peak hours.

Allan Myers, LP of Worcester, Montgomery County is the general contractor on the $42,335,555 project, which is financed with 80% federal and 20% state funds. Construction on the entire project is expected to finish in fall 2025.

See also:

Mayoral Musings: Lansdale Road Projects for 2022

PennDOT to Resurface Six Roads in Hilltown this Summer

Lane Closures Scheduled to Begin Next Week on Route 309 from Hatfield to Richland Township

Lane Closures, Traffic Delays Expected As Work Continues On Route 309

Get Ready for 4 Years of Delays on Rt. 309 Between Hatfield and Quakertown